As the 2025-26 school year approaches, our remodel and construction projects are still a work in progress and will continue throughout the school year. We cannot thank our staff, students & community enough for their ongoing patience & support as we make these upgrades.
South Elementary Restrooms
We had some slow downs with our tiling process during the month of July, which caused delays in starting the finish work. However, we expect the South Elementary restroom remodel to be mostly completed by Open House on August 14th, with some final finish work to be completed afterward.
Take a look at the South School Site Map.
North Elementary Restrooms
The North School project has started to catch up to the South School timeline, but there is a strong possibility that it will not be completed by Open House. Please be prepared for temporary construction conditions during Open House. We have been informed that some partitions are unfortunately not going to be in by the start of school. We are working with the contractors to place temporary partitions so that our restrooms can still be used at the beginning of the school year. These temporary solutions will meet appropriate standards for student safety and privacy until the permanent fixtures are in place.
Take a look at the North School Site Map.
5th Grade Wing Addition
If you’ve been on campus recently, it may seem like progress on the project has slowed, but there have been many moving parts behind the scenes to keep things moving forward. Road construction has encountered a few challenges, but crews are on track to asphalt the main section this week.
Please drive slowly through these areas and remain patient and flexible as we prepare for the start of school. The upper lane closest to the school will become a bus-only lane. While we are working on installing proper signage, please note that this bus lane will remain gravel longer than the lower lane.
Take a look at the 5th Grade Wing Floor Plan.
Fine Arts Improvements
Final finish work is underway in the music room, however, we did run into a delay with flooring and storage units. These items are now scheduled for installation during the week of Open House, so unfortunately, our music and band teachers will not be able to use the room & show off the upgrades at Open House. If your high school student has a music class, please look for those teachers in the HS gymnasium.
The stage is currently having stairs installed, and we continue to work with our audio and lightning companies to begin installation this fall.
Take a look at the HS & JBMS Site Map.
At Warsaw R-IX, our mission is to Engage, Empower, and Collaborate to Ensure Every Student Has Success Every Day. These improvements help us live out that mission—creating learning environments where students and staff can thrive. We’re proud to continue building on a tradition of excellence and working toward a future that empowers every learner.
Stay tuned for more updates—while you wait, you can check out the full Site Map for Prop KIDS.
Thank you for supporting PROP Kids & being patient with the construction across the district!